SLAMM Forum

General Category => Model Formulation & Parameters => Topic started by: YUROK1 on June 01, 2015, 03:40:16 PM

Title: Fixed SLR
Post by: YUROK1 on June 01, 2015, 03:40:16 PM
Is it possible to use  a fixed SLR value,  for example 2.5 meters , and determine when it would be reached under each of the scenarios?
Title: Re: Fixed SLR
Post by: marco.propato on June 02, 2015, 09:52:56 AM
Models predict that SLR rate will continue to increase after 2100. So you need to know what the SLR curves look like after 2100. But just as a approximate estimate, you can use Table 1 of the Technical Documentation and assume that after 2100 SLR increases with the same rate observed between 2075 2100 and calculate when 2.5 m would be reached after 2100. Hope it helps.
Title: Re: Fixed SLR
Post by: YUROK1 on June 03, 2015, 03:07:33 PM
Thank you  :)